In service since February 2014
Narmada–Kshipra link
5 cumecs (about 432 MLD), lifted 348 m over 47 km to Ujjaini, then 66 km by pipe to Triveni.
Rs 432 crore [13]
Prepared by Seion Watertech, Indore · public sources, 25 November 2026
What serves the city today, what is being built, and five proposed measures from the plant inlet to the tap.
treatment capacity in service, seven plants
new capacity under construction
state deadline for Simhastha works [26]
the mela opens; it closes on 27 May [14]
The water's route, and where each measure acts
UF is ultrafiltration and UV is ultraviolet; the next slide shows where each sits.
No costs are given. Who delivers and operates each measure is left open. Sewage is outside this document. Numbers in square brackets refer to the sources on the last slide.
Reading the measures
UF is ultrafiltration. UV is ultraviolet.
Standby UF plant: two 5 MLD blocks in containers, running in parallel on piped Narmada water.
Water ATMs and point-of-use units: built into each unit, straight after the network water comes in.
Sump UV and booster dosing: a reactor on each sump's delivery main, ahead of the chlorine dose.
Water ATMs and point-of-use units: last in the unit, after any storage or chiller tank, just before the tap.
Nowhere else.No UF inside the treatment plantsNo UF at the sumps
Part A · Baseline · supply today
A dam, two tanks, the Kshipra and Narmada water feed the city's plants.
Site figures (2018 study) add up to the 151 MLD reported in February 2026; tanks, mains and connections also 2018. Circles drawn to storage. [1][6][7][8][9]
Part A · Baseline · capacity being added
Ujjain Municipal Corporation · Rs 1,133.67 crore · foundation laid 11 February 2026, phased completion in 24 months.
One scale. Dashed: the gap between the two totals reported for the new plants. The seven existing plants are also to be upgraded. [1][3][4][5]
Part A · Baseline · river and source works
Progress from a state review in June 2026; costs as reported.
In service since February 2014
5 cumecs (about 432 MLD), lifted 348 m over 47 km to Ujjaini, then 66 km by pipe to Triveni.
Rs 432 crore [13]
Under construction
Silarkhedi raised from 5 to 51 MCM (1,800 mcft); dam 22 m high, 6.5 km long. Filled in the monsoon from Sevarkhedi, released at Triveni when needed.
Rs 614.53 crore [10][11]
Due September 2027
30.15 km: 18.15 km cut-and-cover and a 12 km tunnel, 8.15 km of it excavated. Releases below Gambhir Dam.
Rs 919.94 crore [11][12]
Under construction
29.15 km on both banks, from the Shani temple to the Nagda bypass.
Rs 778 crore [12]
Part B · Source and network
Proposed additions to Ujjain's drinking water treatment for Simhastha 2028, from the plant inlet to the storage tanks.
Chlorine dioxide dosed into raw water in place of pre-chlorination.
Inlet of each plant
A complete treatment plant in containers, 10 MLD, for standby and peak days.
Gaughat plant, on piped Narmada water
UV where water enters the mela network; chlorine topped up and measured at the tanks.
Mela-area sumps; overhead tanks
Who delivers and operates each measure is left open. Numbers in square brackets refer to the sources on the last slide.
Part B · Measure 1 of 5 · at the plant inlet
A first oxidant that forms no trihalomethanes, made on site at each plant and dosed into raw water ahead of coagulation.
dose, paced to flow; 50–70% becomes chlorite (WHO: 0.7 mg/L) [16][17]
at the existing plants at 1 mg/L; 200–250 at the new
Limits. Made on site; costlier than chlorine; chlorite and chlorate need routine testing at each outlet; breaks down in sunlight; a pre-oxidant only.
Part B · Measure 2 of 5 · at the Gaughat plant
A complete treatment plant in containers: strainer, coagulant, UF membranes and chlorine. Two 5 MLD blocks, 10 MLD in all, for standby and peak days.
Backwash returns to the plant inlet
of membrane a block, at an assumed 60 to 80 L/m²/h
served by each block at 15 L a day [37]
Limits. It does not replace the new plants: 10 MLD is about 15% of the 2016 mela supply. [38] It needs power, chemicals and operators.
Part B · Measure 3 of 5 · at the sumps and tanks
A UV reactor on each mela sump's delivery main, and chlorine topped up and measured at every sump and overhead tank.
UV at least 40 mJ/cm², after the pumps and ahead of the chlorine dose, with a turbidity meter and a UV sensor. [32]
mela-area sumps: UV and dosing, under tender [25]
overhead tanks in service: dosing
new overhead tanks: dosing
Hypochlorite dosing with a residual analyser: day tank, pump paced to the inflow, readings to one central screen.
Limits. UV needs clear water: filtered water must hold about 1 NTU. It needs steady power and lamp cleaning. Stored hypochlorite forms chlorate in heat. [16] Over 50 dosing sites need a standing team.
Part C · End point
Proposed additions where pilgrims, kitchens and medical units take their drinking water at Simhastha 2028.
public stand posts planned
Ujjain 2016 [27]kiosks near camps, in one zone
Ujjain 2016 [28]tap stands
Prayagraj 2025 [29]water ATMs
Prayagraj 2025 [29]UF and UV built into every unit: water ATMs for the public, a larger point-of-use unit for bulk users.
Mela roads, ghats and parking; kitchens, akharas, camps, medical units
A daily round of chlorine and bacterial tests, logged and shown at the point.
Every water ATM and unit; stand posts and camp connections on a rota
Part C · Measure 4 of 5 · at the drinking water point
UF and UV are built into every unit; they are not separate installations. A water ATM for the public, and a larger point-of-use unit for bulk users.
UV goes last, after any storage or chiller tank, so nothing is stored after it.
UF ≈ 0.01 micron, 12.5 m² per 1,000 L/h, daily pressure-hold test. UV ≥ 40 mJ/cm², outlet shuts on low dose. [32]
The public refill point on mela roads, ghats and parking: 16,000 L in a 16-hour day.
5,300–6,400 peopleA larger skid, not an ATM, plumbed into the tank of a kitchen, akhara, camp or medical unit: 80,000 L a day at 5,000 L/h.
8,900–14,500 peopleLimits. Power and an attendant at every point; UF needs cleaning and UV lamps age; neither removes dissolved salts. UV earns little virus credit here, so the network's chlorine residual still matters. [31]
Part C · Measure 5 of 5 · at the tap
A fixed daily round where the water is taken: free chlorine on the spot, bacteria by sample, every result shown at the point.
Chlorine, UV sensor status, UF pressure check.
Every tap in each zone covered each week.
DPD kit or pocket meter for chlorine; presence-or-absence kit for bacteria, with laboratory confirmation for E. coli.
Limits. Bacteria take a day or more, so chlorine is the same-day signal. Kits indicate; laboratories confirm. Trained staff daily for two months. Testing finds a failure; it does not prevent one.
Summary
Works are due by the end of 2027; the mela runs from 27 March to 27 May 2028.
A first oxidant that forms no trihalomethanes, in place of pre-chlorination.
Spare treatment in containers on piped Narmada water, for standby and peak days.
UV where water enters the mela network; chlorine topped up and measured at the tanks.
UF and UV built into every water ATM and point-of-use unit, with UV last before the tap.
A fixed daily round of chlorine and bacterial tests, logged and shown at the point.
No costs are given. Who delivers and operates each measure is left open. Capacities are proposed for sizing.
Before the numbers are final
Where reports disagree, what the public record does not settle, and what was assumed for sizing.
To be replaced by design values once raw-water data, the contract scope and the mela plan are in hand.
Every figure is from a published report, not department records
Where the record differs, the record is right; corrections are welcome. Not shown, for want of a verified public figure: each Kshipra barrage's storage, the mela-area pipe network, current counts of tanks and connections.