Seion Watertech· Simhastha 2028, drinking water
Overview

Prepared by Seion Watertech, Indore · public sources, 25 November 2026

Drinking water for Simhastha 2028, Ujjain

What serves the city today, what is being built, and five proposed measures from the plant inlet to the tap.

151MLD

treatment capacity in service, seven plants

200–250MLD

new capacity under construction

End 2027

state deadline for Simhastha works [26]

27 Mar 2028

the mela opens; it closes on 27 May [14]

← → to move · F full screen

The water's route, and where each measure acts

Five proposed measures, from the plant inlet to the tap

UF is ultrafiltration and UV is ultraviolet; the next slide shows where each sits.

  1. Raw water
  2. Plant inlet1Chlorine dioxide pre-oxidation
  3. Filters2Standby UF plant
  4. Tanks and sumps3Sump UV and booster dosing
  5. Mela network
  6. Drinking water point4Water ATMs and point-of-use units
  7. The tap5Checks at the tap

No costs are given. Who delivers and operates each measure is left open. Sewage is outside this document. Numbers in square brackets refer to the sources on the last slide.

Reading the measures

UF and UV each appear in two places, and nowhere else

UF is ultrafiltration. UV is ultraviolet.

UF · ultrafiltration

2
The standby plant at Gaughat

Standby UF plant: two 5 MLD blocks in containers, running in parallel on piped Narmada water.

4
Inside every water ATM and point-of-use unit

Water ATMs and point-of-use units: built into each unit, straight after the network water comes in.

UV · ultraviolet

3
At the mela sumps

Sump UV and booster dosing: a reactor on each sump's delivery main, ahead of the chlorine dose.

4
Inside those same units

Water ATMs and point-of-use units: last in the unit, after any storage or chiller tank, just before the tap.

  1. Raw water
  2. Plant inlet
  3. FiltersUF · 2, in parallel at Gaughat
  4. Tanks and sumpsUV · 3, at the sumps
  5. Mela network
  6. Drinking water pointUF · 4, in each unitUV · 4, in each unit
  7. The tap

Nowhere else.No UF inside the treatment plantsNo UF at the sumps

Part A · Baseline · supply today

151 MLD today, from seven plants

A dam, two tanks, the Kshipra and Narmada water feed the city's plants.

Raw water sources

  • Gambhir Dam 63.7 MCMMain source (2,250 mcft), built 1991; also takes Yashwant Sagar overflow and Narmada water.
  • Sahibkhedi tank 12.62 MCM
  • Undasa tank 6.17 MCM
  • Kshipra at GaughatBarrage pool holding Narmada water.
  • Narmada waterLifted by the Narmada–Kshipra link; direct to the Gaughat plant since summer 2026.
  • Groundwater 4.5 MLD86 power-pump tubewells, about 1,328 hand pumps (2016).

Treatment capacity by site, MLD

Ambodiya56.75
Gaughat, on Gambhir water54.48
Gaughat, on Kshipra water27.24
Sahibkhedi8.00
Undasa4.54
151MLD in seven plants, as reported in February 2026
34overhead tanks, ~46.5 ML
~396 kmof mains
54,500connections

Site figures (2018 study) add up to the 151 MLD reported in February 2026; tanks, mains and connections also 2018. Circles drawn to storage. [1][6][7][8][9]

Part A · Baseline · capacity being added

The Hariyakhedi project adds 200 to 250 MLD

Ujjain Municipal Corporation · Rs 1,133.67 crore · foundation laid 11 February 2026, phased completion in 24 months.

151in service+200new plants+50

One scale. Dashed: the gap between the two totals reported for the new plants. The seven existing plants are also to be upgraded. [1][3][4][5]

Hariyakhedi 100 MLDAmbodiya 65–70 MLDGaughat 35–80 MLD
In service todayBeing added
Pipelines~396 km distribution~708 km: 136 clear water, ~40 raw water, 534 distribution; old ACP lines replaced
Overhead tanks34, about 46.5 ML17 more, 600 to 3,000 kL each
Connections~54,50049,087 new household connections
IntakesDam, tanks, Kshipra, NarmadaTwo new intake wells, at Hariyakhedi and Gambhir

Schedule as announced

24-month phased schedule
11 Feb 2026foundation laid
Today
End 2027state deadline
27 Mar–27 May 2028mela

Part A · Baseline · river and source works

Four works feed or protect the Kshipra

Progress from a state review in June 2026; costs as reported.

in service

In service since February 2014

Narmada–Kshipra link

5 cumecs (about 432 MLD), lifted 348 m over 47 km to Ujjaini, then 66 km by pipe to Triveni.

Rs 432 crore [13]

82%
June 2026

Under construction

Sevarkhedi–Silarkhedi

Silarkhedi raised from 5 to 51 MCM (1,800 mcft); dam 22 m high, 6.5 km long. Filled in the monsoon from Sevarkhedi, released at Triveni when needed.

Rs 614.53 crore [10][11]

66%
June 2026

Due September 2027

Kanh closed duct

30.15 km: 18.15 km cut-and-cover and a 12 km tunnel, 8.15 km of it excavated. Releases below Gambhir Dam.

Rs 919.94 crore [11][12]

29.15
km, both banks

Under construction

New ghats

29.15 km on both banks, from the Shani temple to the Nagda bypass.

Rs 778 crore [12]

Part B · Source and network

Three measures at the plants, sumps and tanks

Proposed additions to Ujjain's drinking water treatment for Simhastha 2028, from the plant inlet to the storage tanks.

1

Chlorine dioxide pre-oxidation

Chlorine dioxide dosed into raw water in place of pre-chlorination.

Where

Inlet of each plant

2

Standby UF plant

A complete treatment plant in containers, 10 MLD, for standby and peak days.

Where

Gaughat plant, on piped Narmada water

3

Sump UV and booster dosing

UV where water enters the mela network; chlorine topped up and measured at the tanks.

Where

Mela-area sumps; overhead tanks

Who delivers and operates each measure is left open. Numbers in square brackets refer to the sources on the last slide.

Part B · Measure 1 of 5 · at the plant inlet

1Chlorine dioxide pre-oxidation

A first oxidant that forms no trihalomethanes, made on site at each plant and dosed into raw water ahead of coagulation.

Why

  • The mela draws stored water at its worst. April–May supply is end-of-dry-season dam and tank water: algae, organics, manganese, odour. Raw-water records are not public.
  • Chlorine forms trihalomethanes on it. IS 10500 limits chloroform to 0.2 mg/L and bromodichloromethane to 0.06 mg/L. [15]
  • Chlorine dioxide forms none. It removes algal taste and odour, and oxidises iron and manganese for the filters. [17]
  • It holds its strength as pH rises. Chlorine weakens, and algae push pH up in daylight. [17]

Strength across pH

≤ 1mg/L

dose, paced to flow; 50–70% becomes chlorite (WHO: 0.7 mg/L) [16][17]

151kg/day

at the existing plants at 1 mg/L; 200–250 at the new

Limits. Made on site; costlier than chlorine; chlorite and chlorate need routine testing at each outlet; breaks down in sunlight; a pre-oxidant only.

Part B · Measure 2 of 5 · at the Gaughat plant

2Standby UF plant

A complete treatment plant in containers: strainer, coagulant, UF membranes and chlorine. Two 5 MLD blocks, 10 MLD in all, for standby and peak days.

Why a spare plant

  • The new capacity arrives with no margin. The 200 to 250 MLD runs on a 24-month programme from February 2026, ending about a month before the mela opens on 27 March 2028.
  • Until then, 151 MLD serves city and mela. The 2016 mela alone was planned at 65 MLD for one month; 2028 runs two. [38][14]
  • Peak days should not overload the sand filters. A sand filter's credit against Cryptosporidium assumes filtered water of about 0.3 NTU. [39]
  • A fault on a bathing day has no fallback. No standby treatment is on public record; a spare block covers a filter, pump or clarifier fault.
  • Gaughat already has what a spare plant needs. Narmada water by pipe kept the city on daily supply through summer 2026, and its mains fed the mela's tanks in 2016. [9][38]

Inside the Gaughat plant boundary, as a parallel train

2,600–3,500m²

of membrane a block, at an assumed 60 to 80 L/m²/h

~3.3lakh people

served by each block at 15 L a day [37]

Not proposed elsewhere

Tank plantslow, algal water; small mainsAmbodiyaGambhir runs lowRiver bankbathing waterTrivenino sump or main

Limits. It does not replace the new plants: 10 MLD is about 15% of the 2016 mela supply. [38] It needs power, chemicals and operators.

Part B · Measure 3 of 5 · at the sumps and tanks

3Sump UV and booster dosing

A UV reactor on each mela sump's delivery main, and chlorine topped up and measured at every sump and overhead tank.

Why

  • Chlorine does not stop every organism. Cryptosporidium and Giardia resist it; 22 mJ/cm² of UV earns 4-log credit against both. [15][31]
  • The sump is where all mela water passes. A reactor there covers every stand post; 200 water ATMs serve about 11 to 13 lakh people a day.
  • The standard is set at the tap. At least 0.2 mg/L free chlorine at the consumer end, 0.5 where viral protection is needed. At Prayagraj in 2019, 102 of 521 samples fell short. [15][21]
  • Contamination enters after the plant. Bhagirathpura, Indore, Dec 2025: sewage in a main, over 1,400 ill, 15 deaths linked by an audit. Ujjain reports 20 to 30% leakage and a boil-water advisory. [22][23][24]

At each mela sump

SumpPumpsUVChlorineMain

UV at least 40 mJ/cm², after the pumps and ahead of the chlorine dose, with a turbidity meter and a UV sensor. [32]

Free chlorine, mg/L

Open

mela-area sumps: UV and dosing, under tender [25]

34

overhead tanks in service: dosing

17

new overhead tanks: dosing

Hypochlorite dosing with a residual analyser: day tank, pump paced to the inflow, readings to one central screen.

Limits. UV needs clear water: filtered water must hold about 1 NTU. It needs steady power and lamp cleaning. Stored hypochlorite forms chlorate in heat. [16] Over 50 dosing sites need a standing team.

Part C · End point

Two measures where pilgrims take their water

Proposed additions where pilgrims, kitchens and medical units take their drinking water at Simhastha 2028.

What earlier melas provided

~1,000

public stand posts planned

Ujjain 2016 [27]
85

kiosks near camps, in one zone

Ujjain 2016 [28]
6,500

tap stands

Prayagraj 2025 [29]
200

water ATMs

Prayagraj 2025 [29]
4

Water ATMs and point-of-use units

UF and UV built into every unit: water ATMs for the public, a larger point-of-use unit for bulk users.

Where

Mela roads, ghats and parking; kitchens, akharas, camps, medical units

5

Checks at the tap

A daily round of chlorine and bacterial tests, logged and shown at the point.

Where

Every water ATM and unit; stand posts and camp connections on a rota

Part C · Measure 4 of 5 · at the drinking water point

4Water ATMs and point-of-use units

UF and UV are built into every unit; they are not separate installations. A water ATM for the public, and a larger point-of-use unit for bulk users.

Why

  • The tap is where safety was lost. 2016: 8 of 26 samples from diarrhoea areas were faecal. Prayagraj 2019: 102 of 521 lacked chlorine. [20][21]
  • Bulk users multiply the risk. One kitchen feeds thousands; the larger 2016 outbreak, 42 cases, was in the Dutta Akhara zone. [20]
  • Two independent barriers. UF: 4.9 and 5.8 log for Giardia and Cryptosporidium. UV at 22 mJ/cm²: 4-log credit for both. [18][31]
  • No RO. The NGT directed in 2019 that RO be prohibited below 500 mg/L dissolved solids; UF and UV leave no reject. [33]

Inside every unit

Two kinds of unit [37]

Water ATM~1,000L/h

The public refill point on mela roads, ghats and parking: 16,000 L in a 16-hour day.

5,300–6,400 people
Point-of-use unit2,000–5,000L/h

A larger skid, not an ATM, plumbed into the tank of a kitchen, akhara, camp or medical unit: 80,000 L a day at 5,000 L/h.

8,900–14,500 people

Limits. Power and an attendant at every point; UF needs cleaning and UV lamps age; neither removes dissolved salts. UV earns little virus credit here, so the network's chlorine residual still matters. [31]

Part C · Measure 5 of 5 · at the tap

5Checks at the tap

A fixed daily round where the water is taken: free chlorine on the spot, bacteria by sample, every result shown at the point.

Why

  • The standard is written for the tap. At least 0.2 mg/L free chlorine, and E. coli not detectable in 100 ml. [15]
  • Testing finds the gaps. Prayagraj 2019: 102 of 521 samples short of chlorine, 7 of 48 with bacterial contamination. [21]
  • A plant laboratory cannot see the tap. In 2016 a laboratory at Gaughat tested samples daily, yet 8 of 26 samples from areas reporting diarrhoea showed faecal contamination. [38][20]
  • It is established practice. At the Kapal Mochan Mela: 848 residual chlorine tests, 52 bacteriological samples. [35]

The round

Every water ATM and unitEvery shift

Chlorine, UV sensor status, UF pressure check.

Stand posts and campsDaily rota

Every tap in each zone covered each week.

When a reading is low

  1. TestBelow 0.2 mg/L
  2. CloseThe point shuts
  3. TraceFeeding tank's dosing checked
  4. ShowBoard and control centre [36]

DPD kit or pocket meter for chlorine; presence-or-absence kit for bacteria, with laboratory confirmation for E. coli.

Limits. Bacteria take a day or more, so chlorine is the same-day signal. Kits indicate; laboratories confirm. Trained staff daily for two months. Testing finds a failure; it does not prevent one.

Summary

Five measures, from the plant inlet to the tap

Works are due by the end of 2027; the mela runs from 27 March to 27 May 2028.

1

Chlorine dioxide pre-oxidation

Plant inlet≤ 1 mg/L

A first oxidant that forms no trihalomethanes, in place of pre-chlorination.

2

Standby UF plant

Gaughat plant10 MLD, two blocks

Spare treatment in containers on piped Narmada water, for standby and peak days.

3

Sump UV and booster dosing

Sumps and tanks40 mJ/cm² · 0.5 mg/L

UV where water enters the mela network; chlorine topped up and measured at the tanks.

4

Water ATMs and point-of-use units

Drinking water point1,000–5,000 L/h

UF and UV built into every water ATM and point-of-use unit, with UV last before the tap.

5

Checks at the tap

The tap0.2 mg/L action level

A fixed daily round of chlorine and bacterial tests, logged and shown at the point.

No costs are given. Who delivers and operates each measure is left open. Capacities are proposed for sizing.

Before the numbers are final

Thirteen items to confirm, four reports that differ

Where reports disagree, what the public record does not settle, and what was assumed for sizing.

Where reports differ

New treatment capacityShown: 200 to 250 MLD. 250 MLD: Hariyakhedi 40 + 60, Ambodiya 70, Gaughat 30 + 50 [1][3]. 200 MLD: 100, 65 and 35 [4][5].
Existing treatment capacityShown: 151 MLD in seven plants [1]; plant figures in [6] add to the same. Also reported: 135 MLD in three plants [3].
Sevarkhedi–Silarkhedi costShown: Rs 614.53 crore, Cabinet approval, September 2024. Also: Rs 445 crore, completion targeted for May 2027 [10].
New intake wellsShown: Hariyakhedi and Gambhir [1]. Also: Silarkhedi, Gambhir, Undasa and Sahibkhedi [2].

To be confirmed

  1. Part B
  2. 1New plants: contract scope for pre-oxidation, and commissioning dates
  3. 2How the seven existing plants pre-oxidise today
  4. 3Raw-water analyses at each intake, April to June
  5. 4Filtered-water turbidity and UV transmittance at each plant, April to June
  6. 5At Gaughat: space, spare Narmada supply and spare clear-water pumping
  7. 6What feeds the mela-area sumps, and how many there are
  8. 7Whether the sump-well tender's chlorination covers the drinking water sumps
  9. Part C
  10. 8Whether a tender has followed the water ATM design call, and what it specifies
  11. 9Dissolved solids (TDS) of treated water in the mela network
  12. 10Number and sites of water ATMs
  13. 11Number of kitchens, akharas, camps and medical units to serve
  14. 12Power available at each point
  15. 13Who runs the daily checks, and which laboratory confirms

Assumed for sizing

Chlorine dioxide dose1 mg/L
Standby UF plant10 MLD, two blocks
UF flux, standby plant60–80 L/m²/h
UF flux, water points80 L/m²/h
Booster set point0.5 mg/L
Water ATM1,000 L/h
Point-of-use unit2,000–5,000 L/h
Operating day16 hours
UV dose, sumps and points40 mJ/cm²

To be replaced by design values once raw-water data, the contract scope and the mela plan are in hand.

Every figure is from a published report, not department records

Sources

  1. 1
    Free Press Journal, 11 Feb 2026. Hariyakhedi project scope; 151 MLD in seven plants.
  2. 2
    The Hitavada, 12 Feb 2026. Project sources, tanks, pipelines, connections.
  3. 3
    Patrika, 9 Mar 2025. 250 MLD in five new plants, by site.
  4. 4
    Samachar Aaj, 22 Apr 2025. 200 MLD by site; Silarkhedi at 1,800 mcft.
  5. 5
    IANS, June 2026. 200 MLD plant in the city augmentation scheme.
  6. 6
    Development Alternatives, 2018. Plant capacities, tanks, mains, connections, tubewells.
  7. 7
    WaterAid India and BGMS, 2016. Storage of Gambhir Dam and the two tanks.
  8. 8
    Free Press Journal, 20 Jul 2022 and 23 Jul 2023; Dainik Avantika, 2025. Gambhir Dam capacity, inflow, year built.
  9. 9
    Amar Ujala, 2 Jul 2026. Narmada water delivered to the Gaughat plant.
  10. 10
    Amar Ujala, 5 Jun 2026; The Hitavada, 11 Sep 2024. Sevarkhedi–Silarkhedi works and approval.
  11. 11
    Indian Masterminds, 26 Jun 2026. Progress of 82% and 66%.
  12. 12
    Swarajya, 11 Oct 2026; ANI, 13 Jan 2025; Organiser, 15 Mar 2025. Kanh closed duct and new ghats.
  13. 13
    MEIL; SANDRP, 2014; PTI, 2015; NewsBharati, 19 Jun 2019. Narmada–Kshipra link and pipeline to Triveni.
  14. 14
    ANI, 5 Mar 2024. Mela dates. Free Press Journal. Barrage names.
  15. 15
    Bureau of Indian Standards, IS 10500:2012: residual chlorine, E. coli, trihalomethanes, Cryptosporidium, Giardia.
  16. 16
    World Health Organization, chemical fact sheets, 2022: chlorine, chlorite, chlorate.
  17. 17
    US EPA, Alternative Disinfectants and Oxidants Guidance Manual, 1999, ch. 4, chlorine dioxide.
  18. 18
    US EPA and NSF, Environmental Technology Verification report, ultrafiltration system, July 2000.
  19. 19
    MP Urban Development, Schedule of Rates, Vol. I, Aug 2021, item 22.1, conventional water treatment plant.
  20. 20
    Indian Journal of Public Health, 2020: public health surveillance at Simhastha 2016.
  21. 21
    International Journal of Infectious Diseases, 2020: surveillance at the Prayagraj Kumbh 2019.
  22. 22
    Reports on the Bhagirathpura outbreak, Indore, December 2025 and after: aol.com, Outlook India.
  23. 23
    India TV, 4 Jan 2026: boil-water advisory in Ujjain.
  24. 24
    Dainik Avantika, 2025: leakage in Ujjain's water network.
  25. 25
    Ujjain Municipal Corporation tenders on mptenders.gov.in, read 25 Nov 2026: 2026_UAD_514475_1 (Package 6, Blocks 3 and 4) and 2026_UAD_540310_1 (sump wells and sewerage).
  26. 26
    Government of Madhya Pradesh release, 23 Nov 2026: Simhastha works complete by end of 2027. Deccan Herald.
  27. 27
    India Water Portal, Feb 2016: interview with the chairman of the Simhastha Fair Authority.
  28. 28
    Daily Pioneer, 30 Apr 2016: drinking water kiosks and piped connections at Simhastha.
  29. 29
    Maha Kumbh 2025 official site, Making of Maha Kumbh: tap stands, water ATMs, pipelines.
  30. 30
    Asianet Newsable, 23 Jan 2025: daily output of the Prayagraj water ATMs.
  31. 31
    US Code of Federal Regulations, 40 CFR 141.720(d): UV dose table.
  32. 32
    NSF/ANSI 55 Class A UV systems, 40 mJ/cm² at the alarm set point.
  33. 33
    National Green Tribunal, O.A. 134 of 2015: direction of 20 May 2019 on RO.
  34. 34
    Ujjain Smart City Limited, EOI for temporary water ATMs, 15 Oct 2025, NIT USCL/396.
  35. 35
    The Tribune: water sampling at the Kapal Mochan Mela, Yamunanagar.
  36. 36
    Ujjain Smart City Limited, RFP for an Integrated Command and Control Centre for Simhastha 2028, 20 May 2026.
  37. 37
    Sphere Handbook, water supply standard 1: basic survival water needs.
  38. 38
    Daily Pioneer, 29 Feb 2016: the drinking water plan for Simhastha 2016.
  39. 39
    Health Canada, Guidelines for Canadian Drinking Water Quality, turbidity: filtration credits adapted from US EPA rules.

Where the record differs, the record is right; corrections are welcome. Not shown, for want of a verified public figure: each Kshipra barrage's storage, the mela-area pipe network, current counts of tanks and connections.